Recalculate GenCost's nuclear LCOE — move the assumptions yourself
Energy Realism
a sister site of Unprepared
Presets:
7%
GenCost: 7%
30 yr
GenCost: 30 yr
71%
GenCost: 53–89%
A$13,200/kW
GenCost: ~A$13,200 (post-IDC)
Nuclear LCOE — mature fleet (NOAK)
A$215/MWh
Above the firmed-renewable band.
…as a FIRST Australian build (+120% FOAK)
A$420/MWh
GenCost's own suggested first-of-a-kind premium — shown always, because hiding it is the dishonest move.
Firmed renewables (the fair like-for-like): A$76–131/MWh (wind + solar + storage + transmission, GenCost 2030) — notbare solar at A$35–63. The defaults reproduce GenCost's published A$173–288/MWh across the 53–89% capacity-factor band.