← Energy Realism
Cost2026-10-23· RenewEconomy

Snowy profits steady amid pumped hydro strains, while CEO Barnes sees his take-home benefits sink below $2 million

Image: reneweconomy.com.au

Snowy Hydro reported EBITDA of $756.8 million for 2025-26, a 6% increase, while releasing a revised cost estimate for Snowy 2.0 of up to $25 billion and pushing full commissioning to late 2029. The 2.2-gigawatt pumped hydro project, now subject to repeated cost reforecasts by its contractor Future Generation Joint Venture, has prompted CEO Dennis Barnes to describe the latest blowout as "very disappointing". The company cited the project's "unique nature", "level of risk and technical complexity", and the contractor's "cost estimation challenges" in accounting for the expanded budget.

Where this fits

Snowy 2.0 is a firm, dispatchable storage project meant to anchor Australia's renewable-heavy grid, yet it has become a textbook case of cost and schedule creep in major energy infrastructure. The $25 billion figure, now the working assumption five years into construction, reflects the genuine complexity of firming a weather-dependent system. This is not a failure of the storage concept; it is evidence that firming costs money, time, and engineering rigour, and that these costs belong in any honest accounting of the transition's full price.

What it means

Australia is betting heavily on a single, ballooning pumped hydro scheme to provide the dispatchable backbone for a grid increasingly dependent on wind and solar. Delay and cost blowout on Snowy 2.0 leave the grid more exposed to weather volatility and more reliant on temporary gas-plant extensions while that storage matures. The firming challenge is real and expensive; the question Australia has not answered is whether nuclear, banned by law, might deliver the same service at lower total cost and with no schedule risk.

By the numbers

Taking the article's figure of 1,980 megawatts, at indicative Australian build costs:
What it costs to buildA$4bn–A$6.3bn

at ~A$2000–3200/kW installed. Source: CSIRO GenCost 2024-25. Indicative.

What it generates~6.6 TWh/yr

at a ~38% capacity factor, and only when the wind blows, so it still needs firming.

The same money in nuclear0.3–0.7 GW

enough for 2–6 TWh a year of firm, always-on power, generating for ~60 years. Source: CSIRO GenCost 2024-25 (A$8.5–13.2bn/GW), IAEA capacity factor.

Figures are indicative conversions from the article's stated quantity using published cost, material and capacity factors (CSIRO GenCost, BNEF, IEA, IAEA). Ranges, not precise forecasts.

Go deeper on the numbers

The bigger picture

Energy security is national security. This connects to the wider case at Unprepared: Australia's dependence on a strategic rival, and how ready it is for the world that is coming.

Reported by RenewEconomy. Read the original report ↗