Large wind farm and big battery approved, subject to road rules and threatened bird management plan

NSW's Independent Planning Commission has approved the 804 MW Bullawah wind farm near Hay, with a 358 MW battery, subject to conditions on road upgrades during construction and a management plan for the threatened Plains-wanderer bird. The project, with 141 turbines reaching 300 metres, received approval under a special ruling that prevents court appeal. The IPC acknowledged local council concerns about traffic and environmental impacts alongside submissions from the landowner on agricultural and economic benefits.
Where this fits
Bullawah is another megawatt addition to Australia's renewables fleet, but it highlights two costs the headline obscures. A 358 MWh battery lasting four hours at full output cannot firm 804 MW of wind through a multi-day calm. That firming gap, filled by gas plants that must remain operational and paid, is an invisible infrastructure cost not counted in the project's economic case. Second, the battery's energy-density problem means 718 MWh of lithium cells, processors, and inverters sourced from China's coal-fired supply chain. Australia is betting grid resilience on Beijing's goodwill on materials supply.
What it means
Each large wind-plus-battery approval moves Australia further into a grid architecture that is cheaper per megawatt-hour but more complex and materially dependent than it appears. The 358 MWh battery will not survive a week of low wind without external firming. Australia's energy security now rests not on fuel diversity or domestic capacity, but on weather patterns and uninterrupted access to Chinese battery supply. A firm, long-lived, domestically-buildable alternative, nuclear, remains legislatively banned, foreclosing the one option that requires no firming, no weather hedging, and no strategic mineral dependence.
By the numbers
at ~A$2000–3200/kW installed. Source: CSIRO GenCost 2024-25. Indicative.
at a ~38% capacity factor, and only when the wind blows, so it still needs firming.
enough for 1–2 TWh a year of firm, always-on power, generating for ~60 years. Source: CSIRO GenCost 2024-25 (A$8.5–13.2bn/GW), IAEA capacity factor.
Figures are indicative conversions from the article's stated quantity using published cost, material and capacity factors (CSIRO GenCost, BNEF, IEA, IAEA). Ranges, not precise forecasts.
at ~A$600–1000/kWh installed. Source: BNEF, CSIRO GenCost 2024-25. Indicative.
of average national (NEM) demand if fully dischargeable, then it needs recharging. Storage shifts power, it does not generate it.
lithium, graphite, nickel, copper and cobalt (~72 t lithium content). Replaced roughly every 12 years. Source: IEA, Argonne GREET. Indicative.
~75% of cells are China-made. Source: IEA cell-manufacturing share.
enough for 0–1 TWh a year of firm, always-on power, generating for ~60 years. Source: CSIRO GenCost 2024-25 (A$8.5–13.2bn/GW), IAEA capacity factor.
Figures are indicative conversions from the article's stated quantity using published cost, material and capacity factors (CSIRO GenCost, BNEF, IEA, IAEA). Ranges, not precise forecasts.
Go deeper on the numbers
The bigger picture
Energy security is national security. This connects to the wider case at Unprepared: Australia's dependence on a strategic rival, and how ready it is for the world that is coming.
Reported by RenewEconomy. Read the original report ↗
Related coverage
More batteries, both big and small, mean solar farms don’t have to shut down so often - Renew Economy
Concrete foundations completed for all 18 turbines at first and smallest wind farm to begin construction this year
Australia’s gas generation falls to lowest level since 2000 — OilPrice - UA.NEWS
Renewables Boom Pushes Australia's Gas Power to Quarter-Century Low - Crude Oil Prices Today | OilPrice.com
The numbers, as they move
A short, sourced brief when the figures shift: a transmission blow-out, a supply-chain move, a milestone.