Waroona Renewable Energy Project on track to secure Stage 1 funding

Frontier Energy has secured a project finance debt facility of up to $280 million to fund Stage One of the Waroona Renewable Energy Project in Western Australia. The project combines 132 MW of solar capacity with 81.5 MW of battery energy storage. Funding is on track to proceed.
Where this fits
This is a classic renewables-firming bundle: solar alone cannot meet dispatchable demand, so battery storage is paired with it to create a product the grid can use. The $280 million facility shows the hidden cost of renewables integration. A 132 MW solar plant generates power only when the sun shines; the 81.5 MW battery (around 650 MWh of storage, at typical density) is the cost of making that solar useful. This is firming cost, and it sits on top of the solar cost. A nuclear plant of equivalent firm capacity would be built once, with no weather-dependent shortfall to cover. The batteries also lock Australia into China-dependent supply chains for the critical-materials and cell manufacturing that underpins them.
What it means
Australia is building its grid by layering expensive firming infrastructure over renewable generation, rather than choosing firm, energy-dense sources from the outset. Every MWh the battery stores is an MWh that must first be generated, and every kilowatt of storage capacity is a kilowatt of manufacturing and minerals exposed to strategic dependence. The cost and supply-chain risk are real. They are the price of ruling out the one firm, low-emission alternative nuclear power can offer.
By the numbers
at ~A$1100–1600/kW installed. Source: CSIRO GenCost 2024-25. Indicative.
at a ~24% capacity factor, and only when the sun shines, so it still needs firming.
~80% of modules are China-made. Source: IEA solar supply-chain data.
Figures are indicative conversions from the article's stated quantity using published cost, material and capacity factors (CSIRO GenCost, BNEF, IEA, IAEA). Ranges, not precise forecasts.
Go deeper on the numbers
The bigger picture
Energy security is national security. This connects to the wider case at Unprepared: Australia's dependence on a strategic rival, and how ready it is for the world that is coming.
Xi Jinping and the Purge That Built an Army
The PLA that Xi Jinping inherited in 2012 was modernising, and the one he commands in 2026 is transformed. Part IV of the Unprepared series.
Reported by PV Magazine Australia. Read the original report ↗
Related coverage
What grid-forming kit are Australia’s largest solar–BESS hybrids using?
New four-hour battery storage proposal seeks federal green tick for Australia’s most renewable state grid
SA gives green light for gas to help power future data centres - ABC News & Headlines – Australian Broadcasting Corporation
Concentrated Solar Power (CSP) in Australia: Can It Work Alongside Rooftop Solar? - Energy Matters
The numbers, as they move
A short, sourced brief when the figures shift: a transmission blow-out, a supply-chain move, a milestone.